MWH01 - Our first Data Center in Frankfurt

Resilience and highest uptime values planned from the beginning:

Green Data Centers for the Highest Demands


MWH01 is the name of our first data center campus, which is currently under construction in Frankfurt Seckbach. The symbolic groundbreaking ceremony took place on October 14, 2022.  

Initial space will be phased in during 2024. Completion of the entire campus is planned for 2025.  

The campus has already been let on a long-term basis.

Overview of the data:  
 
  • 6.700m² White Space 
  • 30 MW IT-Load
  • PUE: 1,2
  • Gas extinguishing system for fire protection
  • Recovery of waste heat for heating of office spaces and Concert Hall “Batschkapp”
  • Availability: TIER III+ compliant (Concurrently maintainable)
  • Generator Fuel Autonomy: 48h+
  • Ready-for-Service April 2024
  • LEED Gold certification


The picture shows the first building MWH01.1 of the RZ-Campus MWH01 in Frankfurt Seckbach as of February 2024.

6.700

White Space

30 MW

IT-Load

2024

Ready-for-Service